A functional team member often becomes disruptive during status meetings and attempts to derail progress with the key stakeholders. This team member often discusses why the project will not be successful.
What should the project manager do?

الخيارات

  • A Investigate alternatives for team member needs.
  • B Identify the root cause of the team member's misunderstanding.
  • C Evaluate the engagement needs for stakeholders.
  • D Build trust and influence stakeholders.