A newly hired project team lead was assigned a project using a hybrid delivery approach. As the project onboards a lot of new team members, the lead feels overwhelmed with the effort of explaining the project delivery process to each new team member.
What should the project lead do?

الخيارات

  • A Recommend putting the project temporarily on hold and focus on onboarding and training.
  • B Document the processes and organize a week-long, off-site meeting with the project team.
  • C Use Pareto techniques to identify the knowledge required by the majority of the team.
  • D Develop a training curriculum and schedule training delivery throughout the project.