A project is on schedule. However, during a site visit, a project manager notices that the contractor's productivity is low.
What should the project manager do?

الخيارات

  • A Update the project schedule to align with the contractor's productivity.
  • B Discuss the need to increase productivity with the contractor.
  • C Plan the close-out activities since the project is on schedule.
  • D Assess the opportunity to deliver the project ahead of schedule and introduce a reward system.