اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 431 من 874

كل الأسئلة

A project team has obtained additional team members from different time zones. As a result, there are full-day delays in the work being completed because there are questions from team members from opposite time zones.
What should the project lead do?

الخيارات

  • A Escalate to the project sponsor and request to replace certain team members so the time zones are aligned.
  • B During daily check-ins, compile questions, coordinate with all team members, and agree to meet.
  • C Inform all team members that they are required to check for messages every few hours to ensure fast response times.
  • D Meet each team member during their work hours to ensure all questions are answered in a timely manner.

النقاشات