اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 428 من 874

كل الأسئلة

A project is on its third iteration out of nine. During the daily meetings, the project team realizes that some deliverable approvals are delayed because a key stakeholder is out of the office.
What should the project manager do?

الخيارات

  • A Remove the deliverables from the iteration backlog.
  • B Meet with the stakeholders and request a solution.
  • C Update the issue log and escalate it to the project sponsor.
  • D Ask the team to work on the unblocked deliverables.

النقاشات