In an organization transitioning to agile, the project team is in the norming phase. Team members became uncomfortable when the project manager assigned reporting responsibilities to the newest team member. Team members began questioning the project manager's decision.
What should the project manager do?

الخيارات

  • A Remind team members that administrative decisions are the project manager's duties.
  • B Explain the rationale for delegating responsibilities to team members.
  • C Revoke the delegated responsibilities to keep the team members harmonious.
  • D Invite team members to volunteer for roles for which they feel qualified.