Due to scope changes, some of the risks identified during the initiation phase have materialized into issues. What should the project manager do next?

الخيارات

  • A Submit a change request for additional resources and accept the changes.
  • B Ask the project sponsor to reject high-risk scope changes.
  • C Closely monitor scope changes and implement corrective actions.
  • D Submit a request to access contingency reserves and accept the changes.