A project team wants to change a delivery approach for a project. Team members explain the need for a review of the information-sharing approach to ensure efficient information exchange during the project.
What should the project manager do?

الخيارات

  • A Ask the project sponsor to decide on the best communication strategy.
  • B Review the stakeholder engagement plan with the project team.
  • C Ask the project sponsor to approve funding for a collaboration tool.
  • D Review the communications management plan with the project team.