Two project team members are having difficulty communicating updates and issues. One team member prefers telephone calls for any kind of urgency, whereas the other team member prefers email communication. This difference results in a lack of understanding between the team members and sometimes hinders timely communication.
What should the project manager do?

الخيارات

  • A Provide these team members with feedback that this issue is causing a delay.
  • B Ask the team members to resolve this issue themselves.
  • C Ask the team members to follow the ground rules in the project management plan.
  • D Provide guidance to the team members to resolve the conflicts.