السؤال 404 من 874

كل الأسئلة

A project is nearing the completion of a sprint when the product owner announces that a local regulator has banned part of the deliverable. What should the project manager do?

الخيارات

  • A Complete the sprint and seek a waiver from the regulator.
  • B Add more items to the sprint backlog that will add value.
  • C Complete the sprint, but do not release the deliverable.
  • D Perform a sprint risk assessment and analyze challenges.