اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 387 من 874

كل الأسئلة

A project manager is working on a global project and realizes that one team member is not performing as expected. The project manager meets with the team member to find out what is causing this low performance. The project manager discovers the team member is experiencing conflict and feels uncomfortable with the team. The team member then asks to be moved to another project.
What should the project manager do?

الخيارات

  • A Request human resources (HR) to help.
  • B Ask other team members to be more welcoming.
  • C Confront the issue with the rest of the team directly.
  • D Move the team member to another project.