A project is approaching the closing phase. While preparing for the final steps, the quality system is updated in accordance with new international quality standards, resulting in new deliverable/approval procedures.
Which action should the project manager take?

الخيارات

  • A Escalate the issue to the project sponsor.
  • B Inform the customer that the project will be late.
  • C Apply the new list of approval procedures.
  • D Ask the project team if the scope can be changed.