A multinational company is embarking on an ambitious organizational change project. The objectives of the project include the complete transformation of the organization’s structure, role catalog, and global locations in which supporting services are to be delivered.
What should the project manager advise as an essential component of the project?

الخيارات

  • A A project risk management plan to evaluate and mitigate the risks of change on the performing organization.
  • B A project stakeholder map to assist in understanding which senior executives need to be consulted on the communications management plan.
  • C A panel of subject matter experts (SMEs) that can be consulted for their opinions on how to implement the change project.
  • D A communications management plan and a change management plan to convey the need for change and support the organization.