A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team’s efforts. What should the project manager do in this situation?

الخيارات

  • A Work to understand the key stakeholder's concerns and provide feedback in regular project status reports.
  • B Arrange an ad hoc meeting to address the key stakeholder’s concerns with team members.
  • C Reinforce with the key stakeholder that the project is performing on schedule.
  • D Escalate the situation to the project sponsor because the key stakeholder's behavior is impacting progress.