A project for a new product launch is in a very initial stage and the requirements are evolving. Due to stiff competition in the market, the customer would like to launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year.
What should the project team do?

الخيارات

  • A Execute it as a project with stage gates.
  • B Execute it as a Scrum project.
  • C Execute it using the same
  • D Execute it as a predictive project.