In the beginning of project execution, the project manager finds out that a key resource will be unavailable for two weeks, which could cause a delay to the schedule. What should the project manager do first?

الخيارات

  • A Update the resource management plan and resource allocation chart accordingly.
  • B Update the schedule to reflect the project's changes in duration.
  • C Ask human resources (HR) for a replacement, and update the risk register.
  • D Assign the tasks to another resource, and ask the resource to work double shifts.