The project sponsor on an agile project informed the project lead that an executive would like an update on the project’s progress. What should the project lead do?

الخيارات

  • A Ask the project sponsor or product owner to provide an update since the project lead should be trying to keep the team free from impediments.
  • B Reach out to the project management office (PMO) for status report templates and provide project updates in that format.
  • C Invite the executive to the project's meeting space to determine if the project information radiators meet their needs.
  • D Provide a link to the project's shared drive for the executive to search through for any artifacts that are of interest.