During the closing process, the project manager learns that one deliverable is not meeting customer expectations. How should the project manager proceed?

الخيارات

  • A Meet with the customer to reach agreement on the scope of the deliverable that will satisfy both parties.
  • B Ask the customer to issue a change request with the information to analyze and provide a solution.
  • C Review the deliverable requirements, check the customer approval criteria, and proceed accordingly.
  • D Contact the project sponsor and ask for help in negotiating the closing of the project with the customer.