اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 279 من 874

كل الأسئلة

A key project stakeholder showed interest in the beginning of a complex agile project, but has become less involved as the sprint has progressed due to additional responsibilities. A few sprints later, the key stakeholder rejected a feature deliverable. The team is reworking the rejected deliverable for the next sprint.
What should the project manager have done to avoid this situation?

الخيارات

  • A Involved the key stakeholders in the decision-making process.
  • B Customized stakeholder communications based on the stakeholders’ needs
  • C Analyzed the changes in stakeholder attributes
  • D Documented the project vision and objectives

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.