A project manager is leading a project which shows a trend to exceed the cost baseline. What should the project manager do first to manage the budget?

الخيارات

  • A Meet with the project team to analyze the actual cost to determine deviations.
  • B Inform the stakeholders that the project will be finished over budget.
  • C Ask the project sponsor for assistance in getting the budget back on track.
  • D Issue a change request including the analysis to increase the budget.