اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 270 من 874

كل الأسئلة

A multinational company has a plan to expand their business into a new country where they currently have no presence. A project manager is assigned to initiate this project.
After reviewing the business case, what should be considered first when developing an appropriate implementation strategy?

الخيارات

  • A Evaluate the environmental and regulatory factors and identify high-level risks and assumptions.
  • B Ensure that project sponsors are in agreement on the project deliverables and timeline during the project.
  • C Acquire project resources from the new country to mitigate the risk of uncertainty.
  • D Identify and monitor the risks closely since the company does not have lessons learned for this country.