السؤال 268 من 874

كل الأسئلة

The steering committee has asked a project manager experienced in agile to provide an indication of the time remaining on a medium-sized project. What tools should be used to provide this information?

الخيارات

  • A Story points for the remaining user stories
  • B Surrogate measurements
  • C Analysis of the business requirements document
  • D A release burndown chart