اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 266 من 874

كل الأسئلة

The project sponsor of a major initiative is consistently changing the prioritization of modular work packages. The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope.
What should the project manager do?

الخيارات

  • A Move to a Kanban strategy so that work can be reallocated more easily.
  • B Set up a meeting with the sponsor to explain the importance of keeping a strict sprint cycle.
  • C Decrease the sprint cycle to the average reprioritization request by calculating it in days.
  • D Set up a meeting with the project team and ask for their opinion on what to do.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.