اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 262 من 874

كل الأسئلة

A project manager has been selected to deliver one of an organization’s key flagship solutions. Critical success factors include agility, market adaptation, and a quick response to market offerings.
What are the key activities that the project manager should undertake to ensure company success?

الخيارات

  • A Request more funding from the project sponsor to hire additional skilled resources and to incorporate additional quality in the project delivery approach and outcome.
  • B Review the project objectives with the project sponsor to agree on more realistic and achievable project plans and deliverables.
  • C Conduct periodical reviews of the project plans, objectives, and deliverables to ensure all relevant data are captured to continue making informed project decisions.
  • D Create a business case after performing a market review, and then submit it to the sponsor to modify the project deliverable to meet the newly defined objectives.