The project manager is having difficulty obtaining approval of the project requirements because there is disagreement among the project stakeholders. This issue is putting the project schedule at risk.
What should the project manager do first to facilitate the approval of project requirements?

الخيارات

  • A Identify the source of the disagreement.
  • B Perform a stakeholder analysis.
  • C Review the project charter.
  • D Hold a team-building event.