During project execution, a conflict occurs between the project manager and one of the team members at every project team meeting. The ongoing conflict is preventing tasks and deliverables from being completed. The project manager contemplates changing their leadership style.
What should the project manager do?

الخيارات

  • A Review the set of responsibilities with the team member.
  • B Escalate the situation to the project sponsor.
  • C Review the personnel skill documents.
  • D Avoid the team member to prevent further conflicts.