During the execution of a project, the project manager notices that only one team member has one of the technical skills needed to build the product. The project manager is afraid this might have a future impact on the quality and schedule, because most of the upcoming activities will require at least three people with this specific skill.
What two actions should the project manager take to prevent the team from being unqualified? (Choose 2)

الخيارات

  • A Facilitate a training event with an external trainer.
  • B Teach the entire team the new skill.
  • C Exclude the activities from the roadmap.
  • D Increase the time estimates on the activities that require such abilities.
  • E Encourage working in pairs and knowledge sharing.
  • F Facilitate a training event with an external trainer.
  • G Teach the entire team the new skill.
  • H Exclude the activities from the roadmap.
  • I Increase the time estimates on the activities that require such abilities.
  • J Encourage working in pairs and knowledge sharing.