السؤال 231 من 874

كل الأسئلة

A project manager who is managing a critical project in a multinational company is conducting a progress meeting with all team members. During the meeting, one of the team members states that they are facing a critical problem that will prevent them from completing their assigned task.
What should the project manager do?

الخيارات

  • A Schedule a meeting with the concerned team member to review and update the issue log together.
  • B Ask the team member to raise a change request to assess the issue in detail.
  • C Ask the team member to follow the approved communications management plan to communicate their issue.
  • D Review the risk register with the team member to find the proper response action for this issue.