During the course of a project, a junior team member approaches the project manager for some direction and advice on risk mitigation. How should the project manager respond?

الخيارات

  • A Refer the junior team member to the senior team member who develops the risk mitigation strategy.
  • B Advise the junior team member that the information is available in lessons learned.
  • C Offer guidance and follow up with some developmental activity for the junior team member.
  • D Inform the junior team member that risk mitigation is not part of their work.