A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not be shipped on time, which will impact the schedule.
What should project manager do next to minimize the impact on the project?

الخيارات

  • A Replace the vendor with a new vendor who can offer the component on time.
  • B Add an item to the next status review to make stakeholders aware of the vendor issue.
  • C Review and update the issue log and determine if any alternative components can be offered.
  • D Schedule a meeting with all stakeholders to extend the project deadline.