اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 223 من 874

كل الأسئلة

A new project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25%. The project manager updated the risk register and kept the project running as normal. The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information.
What should the project manager have done to avoid this?

الخيارات

  • A Ensured the risk tolerance of the company was properly updated.
  • B Provided a proper risk response.
  • C Implemented the stakeholder engagement plan correctly.
  • D Implemented the communications management plan properly.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.