A new project manager learns the work assigned to the team has already been decomposed to its lowest level. The project manager reviews the work and feels some additional, useful information is missing.
What should the project manager review?

الخيارات

  • A The business requirement documents (BRD)
  • B The WBS dictionary
  • C The requirements traceability matrix
  • D The project charter and scope statement