The programming activities of a project were planned to last 35 days per module, but the programming of the first module has taken 45 days. What should the project manager do?

الخيارات

  • A Submit a change request to the project sponsor to change the schedule.
  • B Ask the team to work overtime to complete the deliverable on time.
  • C Check the scope to verify if there is scope creep and get the project on schedule.
  • D Evaluate the situation and identify ways to compress the schedule without impacting baselines.