The project manager has learned that the project sponsor is unhappy with the development of the project requirements. To realign the project with the sponsor's expectations, what should the project manager do?

الخيارات

  • A Review the risk management plan.
  • B Perform a stakeholder evaluation.
  • C Review the project goal diagram with the team.
  • D Confirm which templates the team should be using.