A marketing team is planning for a multiyear initiative that will include a lot of cross-functional stakeholders. The project manager has been assigned and is now in the project planning phase.
What item(s) should the project manager develop first?

الخيارات

  • A A communications management plan that addresses the team's needs
  • B A product backlog and identification of the features to be delivered
  • C A risk management plan to incorporate known risks
  • D A business case and scope document